25.08.2005
Currently, construction works are completed to the following stage: 100% of the basement floor skeleton, 90% of the basement floor covering, the 3rd floor of the skeleton of the 1st, 2nd and 3rd block completed,...
22.06.2005
Currently, construction works are completed to the following stage: 100% of the basement floor skeleton, 70% of the basement floor covering, the 3rd floor of the skeleton of the 2nd block completed, the 1st floor of the skeleton of the 1st and 3rd block completed...
31.05.2005
Currently, construction works are completed to the following stage: 100% of the basement floor skeleton, 60% of the basement floor covering, the 2nd floor of the skeleton of the 2nd block completed, construction of the 3rd floor...
10.05.2005
At this stage, 90% of the underground floor skeleton, 60% of the garage floor covering and the skeleton of the ground floor of the building blocks 2 and 3 are constructed.
04.03.2005
!!! Company “Interhaus” announces beginning of sales in dwelling complex “Sea Castle”. Limited supply. With all questions concerning purchasing please contact sales department of company “Interhaus”. Office phone (371) 7811156. Mobile (371) 6459962. Helena.